- Ore processed was up 28% to 67,569 tonnes;
- Metal production increased 22% to a record 680,212 silver equivalent ounces ("Ag eq oz"), at a 60:1 silver:gold ratio;
- Silver production rose 6% to 396,730 silver ounces ("Ag oz");
- Gold production increased 70% to a record 3,994 gold ounces ("Au oz"); and
- Land Use Permit for
San Ignacio was received.
"We are pleased to report both record total metal production and gold production for the second quarter," stated
"Following the addition of a new Vice President, Operations and Vice President, Safety, Health & Environment in the first quarter, we welcome two new mine-site Safety Superintendents in Q2. Our safety record has improved through the quarter, the Rayas Shaft rehabilitation is nearing completion and we are proceeding with improvements to the tailings dams at
Despite an improvement in grades over the first quarter, we caution that operating margins will remain weak for the second quarter due primarily to the severe drop in silver and gold prices over the quarter. In addition, the impact of improved grades will not be substantially reflected in the margins and unit costs for the quarter as most of the concentrate sales will reflect production from the prior period at lower grades. This factor will also impact reported cash costs for the period.
| Consolidated Q2 Operations Summary | Q2 2013 | Q2 2012 | Change | Q2 2013 | Q1 2013 | Change |
| Ore processed (tonnes milled) | 67,569 | 52,956 | 28% | 67,569 | 69,540 | (3)% |
| Silver equivalent ounce production 1 | 680,212 | 555,721 | 22% | 680,212 | 607,501 | 12% |
| Silver ounce production | 396,730 | 374,723 | 6% | 396,730 | 369,624 | 7% |
| Gold ounce production | 3,994 | 2,353 | 70% | 3,994 | 3,144 | 27% |
| Lead production (tonnes) | 243 | 244 | 0% | 243 | 286 | (15)% |
| Zinc production (tonnes) | 411 | 351 | 17% | 411 | 449 | (8)% |
| Total underground development (m) | 4,044 | 4,305 | (6)% | 4,044 | 4,123 | (2)% |
| Underground diamond drilling (m) | 6,907 | 6,814 | 1% | 6,907 | 7,540 | (8)% |
1 Silver equivalent ounces for 2013 were established in
For the second quarter, the
| Guanajuato Q2 Operations Summary | Q2 2013 | Q2 2012 | Change | Q2 2013 | Q1 2013 | Change |
| Ore processed (tonnes milled) | 52,917 | 40,964 | 29% | 52,917 | 52,545 | 1% |
| Silver equivalent ounce production 1 | 466,925 | 359,063 | 30% | 466,925 | 399,417 | 17% |
| Silver ounce production | 236,454 | 226,284 | 4% | 236,454 | 222,906 | 6% |
| Gold ounce production | 3,841 | 2,213 | 74% | 3,841 | 2,942 | 31% |
| Ag grade (g/t) | 159 | 189 | (16)% | 159 | 148 | 8% |
| Au grade (g/t) | 2.47 | 1.82 | 36% | 2.47 | 1.93 | 28% |
| Ag recovery (%) | 87.2% | 91.1% | (4)% | 87.2% | 89.0% | (2)% |
| Au recovery (%) | 91.5% | 92.3% | (1)% | 91.5% | 90.0% | 2% |
| Total underground development (m) | 1,790 | 1,682 | 6% | 1,790 | 1,867 | (4)% |
| Underground diamond drilling (m) | 6,426 | 6,223 | 3% | 6,426 | 7,134 | (10)% |
1 Silver equivalent ounces for 2013 were established in
The lower levels of the Cata and
Gold grades increased significantly, with the most meaningful impact coming from
Underground development at
Exploration development at Cata was focused on defining the continuity of the Veta Madre at the 525 metre level, resulting in high grade intersections and expanding the known mineralized resources.
The
Exploration drilling was carried out using four underground drill rigs, guiding the mining activities with more accurate definitions of mineralized zones. For the quarter, diamond drilling totaled 6,426 metres, up 3% compared to the same period in 2012. Exploration drilling at deep Cata between the 525 and 540 metre levels returned excellent results and demonstrated the potential for the continuity of silver-gold mineralization to depth.
The development of the Guanajuatito main ramp was temporarily suspended to put in place the development required to support an exploration drilling program to upgrade the mineral resources between the 245 and 390 metre levels. This program will commence during the third quarter.
The Rayas shaft is undergoing a thorough rehabilitation to improve safety and efficiency. The rehabilitation is expected to be finalized by mid third quarter. Once completed, this investment is expected to improve the transportation of personnel to their work places and increase operational efficiencies by reducing transportation times.
The Cata processing plant is being upgraded by installing a new filter press that will maximize the rate of filtration and deliver a dryer final concentrate. This will reduce concentrate loss and electricity consumption. The new filter press installation is expected to be completed by mid-third quarter. The
For the second quarter, 14,652 tonnes were processed at Topia, up 22% compared to the same period in 2012, at grades of 376g/t Ag, 0.57g/t Au, 1.79% lead ("Pb") and 3.05% zinc ("Zn"). Metal production included 160,276 Ag oz, 153 Au oz, 243 Pb tonnes, and 411 Zn tonnes, or 213,287 Ag eq oz, which is 8% up over the same period in 2012. Plant metallurgical performance was satisfactory with metal recoveries of 90.6% for silver, 57.0% for gold, 92.5% for lead, and 91.9% for zinc.
| Topia Q2 Operations Summary | Q2 2013 | Q2 2012 | Change | Q2 2013 | Q1 2013 | Change |
| Ore processed (tonnes milled) | 14,652 | 11,992 | 22% | 14,652 | 16,995 | (14)% |
| Silver equivalent ounce production 1 | 213,287 | 196,658 | 8% | 213,287 | 208,084 | 3% |
| Silver ounce production | 160,276 | 148,439 | 8% | 160,276 | 146,718 | 9% |
| Gold ounce production | 153 | 140 | 9% | 153 | 202 | (24)% |
| Lead production (tonnes) | 243 | 244 | 0% | 243 | 286 | (15)% |
| Zinc production (tonnes) | 411 | 351 | 17% | 411 | 449 | (8)% |
| Ag grade (g/t) | 376 | 424 | (11)% | 376 | 300 | 25% |
| Au grade (g/t) | 0.57 | 0.56 | 2% | 0.57 | 0.65 | (12)% |
| Ag recovery (%) | 90.6% | 90.7% | 0% | 90.6% | 89.0% | 2% |
| Au recovery (%) | 57.0% | 64.3% | (11)% | 57.0% | 57.0% | 0% |
| Total underground development (m) | 2,254 | 2,623 | (14)% | 2,254 | 2,256 | 0% |
| Underground diamond drilling (m) | 481 | 591 | (19)% | 481 | 406 | 19% |
1 Silver equivalent ounces for 2013 were established in
The majority of the metal production during the quarter was obtained from the 1522 and Durangueno mines, followed closely by the
Underground development at Topia consisted of 2,254 metres, down 14% compared to the same period in 2012. The development program for the quarter was focused on deepening main ramps at the
Taking into account constantly changing metal prices, management continues to conduct mine by mine reviews to determine the profitability of individual mines at Topia, thereby determining where to best concentrate the mining efforts and reduce costs. To date, two of the fourteen mines have been temporarily shut down, and supplemented with increased production at other more profitable mines.
Improvements are being made to the Topia processing plant by the installation of a cone crusher that will significantly increase the crushing capacity at the plant and reduce maintenance and electricity costs. In addition, a performance improvement analysis is being undertaken in order to further optimize the mill and flotation sections of the plant.
The Company received approval of the Land Use permit earlier than anticipated during the second quarter and submitted a revised Environmental Impact Assessment which is expected to be approved by the end of the third quarter.
A new mine plan is being compiled for
An infill and extension drilling campaign is anticipated to begin in September at
El Horcon
A surface drill program consisting of 24 drill holes for a total of 2,156 metres was completed during the second quarter. The program was laid out along 650 metres of strike length on the Diamantillo vein and also tested various splays and nearby parallel structures and veins.
Assay results have been received and are being compiled and interpreted. A wireframe and 3D model are being constructed such that the continuity of grade and vein widths can be determined. An internal resource estimate and preliminary economic assessment will be prepared in the third quarter.
Outlook
With first half production totaling 1,287,713 silver equivalent ounces, the Company is on track to meet its guidance of 2.4 to 2.5 million silver equivalent ounces for fiscal 2013.
As precious metals prices dropped significantly in the second quarter, the Company has heightened its focus on improving and strengthening the operational efficiency of its operations. Cash cost guidance is being reviewed and the Company will provide an update in our second quarter earnings release, expected in early August.
ABOUT GREAT PANTHER
For further information, please visit the Company's website at www.greatpanther.com.
This news release contains forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of the Securities Act (